WhiteWater, along with its joint venture (JV) partners Devon Energy, Diamondback Energy, Western Midstream Partners (WES) and MPLX, has reached a final investment decision (FID) to construct the Solitude Pipeline System in the US.
The pipeline system will feature two 48in natural gas pipelines designed to transport supplies from the Permian Basin to a hub in Katy, Texas, near the Gulf coast.
The project will be managed by the Solitude Pipeline System JV and is supported by long-term transportation agreements with mainly investment-grade shippers.
Commissioning of the Solitude Pipeline System is dependent on receiving customary regulatory and other approvals, with service targeted to commence in the second half of 2029.
The project's initial phase will provide a capacity of approximately 2.25 billion cubic feet per day (bcf/d) in late 2029, with an additional 2.25bcf/d expected in 2030.
#whitewater #Devon #diamondback #western
The pipeline system will feature two 48in natural gas pipelines designed to transport supplies from the Permian Basin to a hub in Katy, Texas, near the Gulf coast.
The project will be managed by the Solitude Pipeline System JV and is supported by long-term transportation agreements with mainly investment-grade shippers.
Commissioning of the Solitude Pipeline System is dependent on receiving customary regulatory and other approvals, with service targeted to commence in the second half of 2029.
The project's initial phase will provide a capacity of approximately 2.25 billion cubic feet per day (bcf/d) in late 2029, with an additional 2.25bcf/d expected in 2030.
#whitewater #Devon #diamondback #western